Contents

Executive summary

1       Introduction

1.1      Introduction

2       Project Organization and Construction Progress

2.1      Project Organization

2.2      Construction Progress

2.3      Summary of Environmental Submissions

3       Construction Noise Monitoring

3.1      Monitoring Requirements, Frequency and Duration

3.2      Monitoring Locations

3.3      Monitoring Equipment

3.4      Monitoring Methodology

3.5      Monitoring Schedule

4       Ecology Monitoring

4.1      General

4.2      Monitoring Requirement

4.3      Inspection Findings

5       Landscape & Visual Monitoring

5.1      General

5.2      Inspection Findings

6       Site Inspection

6.1      Requirements

6.2      Findings / Deficiencies During the Reporting Period

7       Environmental Complaint, Summons and Prosecution

7.1      Environmental Complaint, Summons and Prosecution

8       Implementation Status of Mitigation Measures

8.1      General Requirements

8.2      Tentative Construction Activities in the Coming Month

8.3      Key Issues for the Coming Month

9       Conclusion

 

A.      Project Location

B.      Project Organisation

C.      Implementation Schedule for Environmental Mitigation Measures

 

  


Executive summary

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Gammon Engineering & Construction Company Limited, to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for Ocean Park Tai Shue Wan Development Water World.

This is the 51st monthly EM&A report for the construction phase of Waterpark Main Building Works submitted under Condition 3.4 of the Environmental Permit (No. EP-487/2014/A). This report summarises the findings on EM&A during the period from 1 to 31 August 2021.

Reporting Changes

For the EM&A programme, the proposal for suspension of the construction phase environmental monitoring (including weekly noise monitoring and environmental site audits) by end of June 2021 was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021.

Environmental Monitoring and Audit Progress

Proposal to suspend impact monitoring for noise was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the last weekly noise monitoring event was conducted on 30 June 2021, while no impact monitoring for noise was conducted in the Reporting Period.  

Ecological, landscape and visual inspection conducted alongside the environmental site audits have been suspended as approved on 6 July 2021. Therefore, the last inspection event for ecological, landscape and visual monitoring was conducted on 25 June 2021 while no inspections were conducted in the Reporting Period.

With the completion of landscape planting and other greening works in the reporting month, the EM&A programme of construction phase has been completed in August 2021.

Exceedance of Action and Limit Levels

Exceedance of Action or Limit Levels for noise levels was not applicable for the Reporting Period as the noise monitoring has been suspended as approved.

Record of Complaints

There was no record of complaints received in the Reporting Period.

Record of Notification of Summons and Successful Prosecutions

There were no record of notification of summons and successful prosecution in the Reporting Period.

Site inspection

Proposal to suspend site inspection was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the last weekly environmental site inspection was conducted on 29 June 2021 while no site inspection was undertaken in the reporting period.

Future Key Issues

There are no future key issues concerned as minor defect works have been completed.

 

 

 

1        Introduction

1.1        Introduction

On 27 August 2014, the Environment Impact Assessment (EIA) Report and Environmental Monitoring and Audit (EM&A) Manual (Register No.: AEIAR-184/2014) for the “Tai Shue Wan Development at Ocean Park” (the Project) was approved and an Environmental Permit (EP) (Permit No.: EP-487/2014) was issued to the Ocean Park Corporation (Project Proponent).

The current valid EP (Permit No.: EP-487/2014/A) was issued on 10 January 2018 based on the Variation of Environmental Permit No. VEP-539/2017 which comprise variation of project boundary, location of sump pit and size of rising main. The Project location is indicated in Appendix A.

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Gammon Engineering & Construction Company Limited to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit for the Ocean Park Tai Shue Wan Water World Project.

As part of the EM&A program, baseline monitoring for the required parameters including background noise, landscape & visual baseline review and baseline ardeid inspection were carried out between 24 October 2014 and 10 December 2014 by the environmental consultants of Ocean Park Corporation. Furthermore, the baseline monitoring report which verified by the previous Independent Environmental Checker (IEC) was submitted to EPD and endorsed in December 2014.

The previous contract (Contract No.: TSW-C004) of Site Formation and Foundation Works has been completed since 31 May 2017, the next construction phase (Contract No.: TSW-C006) for the Ocean Park Tai Shue Wan Development was handed over to Gammon Engineering & Construction Company Limited on 31 May 2017.

This is the 51st monthly EM&A report summarizing the findings of EM&A activities for the Project during the Reporting Period from 1 to 31 August 2021.

The proposal for suspension of the construction phase environmental monitoring (including weekly noise monitoring and environmental site audits) by end of June 2021 was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the last construction phase environmental monitoring events were completed in June 2021 and there were no environmental monitoring or site audits in this Reporting Period.

 


 

2        Project Organization and Construction Progress

2.1        Project Organization

The project organization is shown in Appendix B.  The responsibilities of respective parties are: 

Ocean Park Corporation 

Ocean Park Corporation is the Project Proponent and the Permit Holder of the EP for the development of the Project and will assume overall responsibility for the project.  An Independent Environmental Checker (IEC) shall be employed by Ocean Park Corporation to audit the results of the EM&A works carried out by the ET. 

Environmental Protection Department (EPD) 

EPD is the statutory enforcement body for environmental protection matters in Hong Kong.

Project Management Representative (PMR) of Ocean Park Corporation 

The PMR is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the ER with respect to EM&A are: 

    Monitor the Contractors’ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness 

    Monitor Contractors’, ET’s and IEC’s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual 

    Facilitate ET’s implementation of the EM&A programme  

    Participate in joint site inspection by the ET and IEC  

    Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance 

    Adhere to the procedures for carrying out complaint investigation  

    Liaison with the related government departments, ET, IEC, the Contractor and the other 

Contractors of the Project discussing regarding the cumulative impact issues.  

The Contractor 

The duties and responsibilities of the Contractor are: 

    Comply with the relevant contract conditions and specifications on environmental protection  

    Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of EM &A Facilitate ET’s monitoring and site inspection activities  

    Participate in the site inspections by the ET and IEC, and undertake any corrective actions  

    Provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts  

    Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans  

    Implement measures to reduce impact where Action and Limit levels are exceeded 

    Adhere to the procedures for carrying out complaint investigation  

Environmental Team (ET) 

The ET should be employed by the Contractor to conduct the EM&A programme. The ET should be managed by the ET Leader.  ET Leader should have relevant professional qualifications in environmental control and possess at least seven years’ experience in EM&A. Suitably qualified professional and technical staff should be included in the ET, and resources for the implementation of the EM&A programme should be allocated in the time under the Contract, to enable fulfilment of the Project’s EM&A requirements as specified in the EM&A Manual during construction of the Project. The ET shall include qualified botanist/ecologist for the ecological service and a Registered Landscape Architect for review of implementation of landscape and visual mitigation measures. The ET should report to the OPC and the duties should include:

    to monitor and audit various environmental parameters as required in the Approved EM&A Manual; 

    to analyse the EM&A data, review the success of EM&A programme and the adequacy of mitigation measures implemented, confirm the validity of the EIA predictions, and identify any adverse environmental impacts arising; 

    to monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications; 

    to audit environmental conditions on site; 

    to report on the EM&A results to EPD, the ER, the IEC and Contractor or their delegated representatives; 

    to recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans; 

    to liaise with the IEC on all environmental performance matters, and ensure timely submission of all relevant EM&A pro forma for IEC’s approval; 

    to provide advice to the Contractor on environmental improvement, awareness and enhancement matters, etc. on site; 

    to adhere to the procedures for carrying out complaint investigation; 

    to prepare reports on the environmental monitoring data and the site environmental 
conditions; 

    to submit the EM&A report to Director of Environmental Protection (DEP) timely; 

    to review proposals of mitigation measures from the Contractor in case of exceedance of Action and Limit levels, in accordance with the Event and Action Plan; and 

    to carry out site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and mitigation measures.

Independent Environmental Checker (IEC)   

The IEC is empowered to audit the environmental performance of construction, but is independent from the management of construction works.  As such, the IEC should not be in any way an associated body of the Contractor or the ET for the Project.  The IEC should be employed by OPC prior to the commencement of the construction of the Project.  The IEC should be a person who has relevant professional qualifications in environmental control and at least seven years’ experience in EM&A and environmental management. The duties and responsibilities of the IEC are: 

    to provide proactive advice to the ER and OPC on EM&A matters related to the project; 

    to review and verify the monitoring data and all submissions in connection with the EP and EM&A Manual submitted by the ET; 

    to arrange and conduct regular, at least monthly site inspections of the works during the construction phase, and to carry out ad hoc inspections if significant environmental problems 
are identified; 

    to check compliance with the agreed Event and Action Plan in the event of any exceedance; 

    to check compliance with the procedures for carrying out complaint investigation; 

    to check the effectiveness of corrective measures; 

    to feedback audit results to the ET by signing off relevant EM&A pro forma; 

    to check that mitigation measures are effectively implemented; 

    to report the works conducted, and the findings, recommendations and improvements of the site inspections, after reviewing ET’s and Contractor’s works, the ER and OPC on a monthly basis; 

    to verify the investigation result of the environmental complaint cases and the effectiveness of corrective measures; 

    to verify EM&A report that has been certified by the ET leader; and 

    to audit EIA recommendations and requirements against the status of implementation of environmental mitigation measures on site.

2.2        Construction Progress

Construction activities that have the potential to cause significant environmental impacts have already been completed before June 2021 while the remaining site activities were merely related to minor defect and cleaning works (refer to Monthly EM&A Report No. 49) which were also completed in the reporting period. On the other hand, greening works as stated in the approved Visual and Landscape Plan have been completed in the reporting period.

The proposal for suspension of the construction phase environmental monitoring (including weekly noise monitoring and environmental site audits) by end of June 2021 was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the weekly noise monitoring and environment site inspections as well as the ecological, landscape and visual inspections alongside the environmental site audits have been suspended from July 2021.

2.3        Summary of Environmental Submissions

Summaries of validity permits, licenses, and/or notifications on environmental protection for the Project are presented in Table 1. 

Table 1: Status of Environmental Licenses and Permits of the Project

Type of Permit/ License 

Submission Date

Reference/ 

License No. 

Date of Issue 

 

Date of Expiry 

Status

Environmental Permit

/

EP-487/2014/A

10-Jan-18

N/A

Valid

Variation of Environmental Permit

18-Dec-17

Application No.
VEP-539/2017

10-Jan-18

N/A

Valid

Environmental Permit

/

EP-487/2014

27-Aug-14

N/A

Superseded

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

15-Mar-17

414651

N/A

N/A

Valid

Application for a Billing Account for Disposal of Construction Waste

14-Dec-16

Account No. 7026786

28-Dec-16

N/A

Valid

Discharge Licence under WPCO
WT00028196-2017

15-Mar-17

414650

29-May-17

31-May-22

 

Valid

Registration as a Chemical Waste Producer
(WPN: 5213-176-G2785-01)

21-Apr-17

415966

31-May-17

N/A

Completed

Construction Noise Permit under NCO
GW-RS0439-17

26-Apr-17

416080

15-May-17

29-Dec-17

Superseded

Construction Noise Permit under NCO

GW-RS0825-17

8-Sep-17

420985

22-Sep-17

21-Mar-18

Superseded

Construction Noise Permit under NCO

GW-RS1024-17

3-Nov-17

422922

21-Nov-17

16-May-18

Superseded

Construction Noise Permit under NCO

GW-RS0356-18

16-Apr-18

432628

30-Apr-18

16-Nov-18

Superseded

Construction Noise Permit under NCO

GW-RS0469-18

18-May-18

433713

04-Jun-18

30-Nov-18

Superseded

Construction Noise Permit under NCO

GW-RS1151-18

23-Nov-18

439700

07-Dec-18

06-Jun-19

Superseded

Construction Noise Permit under NCO

GW-RS0345-19

03-Apr-19

434093

18-Apr-19

17-Oct-19

Superseded

Construction Noise Permit under NCO

GW-RS0726-19

22-Jul-19

447459

25-Jul-19

01-Feb-20

Superseded

Construction Noise Permit under NCO

GW-RS0034-20

07-Jan-20

452524

21-Jan-20

28-Jul-20

Superseded

Construction Noise Permit under NCO

GW-RS0347-20

13-May-20

456050

29-May-20

27-Nov-20

Superseded

Construction Noise Permit under NCO

GW-RS0874-20

06-Nov-20

EPIC ref. NO.#002100418

27-Nov-20

26-May-21

 

Superseded

Construction Noise Permit under NCO

GW-RS0308-21

20-Apr-21

EP831/H16/RS0308-21

26-May-21

24-Nov-21

 

Valid

 

In accordance with the EP stipulation, the required documents submitted to EPD for retention are as listed below:

    Project Layout Plans 

    Management Organization of Main Construction Companies 

    Detailed Vegetation Survey Report 

    Woodland Compensation Plan 

    Ardeid Inspection Report 

    Short-nosed Fruit Bat Inspection Report 

    Baseline Monitoring Report Revision A of the Project

    Ecological Enhancement Plan

    Visual and Landscape Plan

 

 

 

3        Construction Noise Monitoring

3.1        Monitoring Requirements, Frequency and Duration

Construction noise is one of the key environmental issues during the construction phase of the Project in accordance to the approved EM&A Manual. Following the requirements in the EM&A Manual, continuous noise monitoring for A-weighted levels Leq, L10, L90 shall be undertaken once per week during the construction phase. Measurement of Leq(30min) between 07:00-19:00 hours on normal weekdays.

If construction works are necessary to be carried out at other time periods, i.e. restricted time period (19:00-07:00 the next morning and whole day on public holidays) (hereinafter referred as “the restricted hours”), three consecutive Leq(5min) measurements shall be recorded, while complying specific conditions as stipulated on the Construction Noise Permit (CNP). Supplementary information for data auditing and statistical results such as L10 and L90 shall also be obtained for reference. Summary of these monitoring requirements is shown in Table 2.

Table 2: Noise Monitoring Parameters

Monitoring Station

Parameters

NM1A and NM2

      Leq(30min) on normal working days (Monday to Saturday) 07:00-19:00 except public holiday;

      3 sets of consecutive Leq(5min) during restricted hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday when applicable, and

      Supplementary information for data auditing and statistical results such as L10 and L90 shall also be obtained for reference

The baseline results form the basis for determining the environmental acceptance criteria for the impact monitoring. According to the approved EM&A Manual with baseline monitoring results, construction noise criterion, namely Action and Limit levels proposed are listed in Table 3.

Table 3: Action and Limit Levels for Construction Noise

Monitoring Location

Action Level

Limit Level in dB(A)

NM1A and NM2

When one or more documented

complaints are received

70 dB(A)1,2

Note:      1. Acceptable noise levels for school should be reduced to 65 dB(A) during examination period
2. If works are to be carried out during restricted hours, the conditions stipulated in the CNP must be followed.

3.2        Monitoring Locations

Two designated noise monitoring locations were established in the EM&A (refer to Monthly EM&A Report No. 49). After the baseline monitoring, alternative location NM1A has been proposed by MMHK due to rejection of the monitoring location set up at NM1. The proposal was verified and agreed by EPD in the Baseline Monitoring Report. The construction noise monitoring locations for the Project are shown in Table 4.

Table 4: Impact Monitoring locations

Monitoring location

Descriptions

Type of measurement

NM1A

Slope near Victoria Shanghai Academy (VSA) to replace NM1 of the VSA

Free field

NM2

Hong Kong Juvenile Care Centre (HKJCC)

Facade

3.3        Monitoring Equipment

Integrating sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked using an acoustic calibrator. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in ms-1. The acoustic calibrator and sound level meter to be used in the impact monitoring will be calibrated yearly.

Noise monitoring equipment used for monitoring is listed in Table 5.

Table 5: Noise Monitoring Equipment

Equipment

Model

Integrating Sound Level Meter

Rion NL-52

Calibrator

Larson Davis CAL200

Portable Wind Speed Indicator

Anemometer/ Lutron AM-4201

3.4        Monitoring Methodology

Field Monitoring

    Sound Level Meter was set up on a tripod at a height of at least 1.2 m above ground.

    Noise measurements were taken in terms of the A-weighted equivalent sound pressure level (Leq) measured in decibels (dB). Supplementary statistical results (L10 and L90) were also obtained for reference.

    Free field measurement was made at NM1A while facade measurement was made at NM2.

    The battery condition was checked to ensure the correct functioning of the meter.

    Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94 dB at 1 kHz. The checking was performed before and after the noise measurement.

    During the monitoring, all noise measurements would be performed with the meter with Fast time weighting and on the A-weighted equivalent continuous sound pressure level (Leq). Leq(30min) as the monitoring parameter for the time period between 0700-1900 hours on weekdays; and also Leq(15min) in three consecutive Leq(5min) measurements would be used as monitoring parameter for other time periods (e.g. during restricted hours), if necessary. In addition, any site observations and noise sources were recorded on a standard record sheet.

    A correction of +3 dB(A) was made to the free field measurement.

    Noise measurements were not made in fog, rain, wind with a steady speed exceeding 5 ms-1 or wind with gust exceeding 10 ms-1.

Equipment calibration

    The sound level meter and calibrator are calibrated and certified by a HOKLAS accredited laboratory at yearly intervals.

Meteorological Information

Meteorological information was extracted from “the Hong Kong Observatory Wong Chuk Hang Station” to provide the humidity, wind speed, wind direction and temperature etc. as background weather information.

Derivation of Action/Limit (A/L) Levels

According to the approved EM&A Manual and baseline monitoring results, Action and Limit levels criterion proposed for construction noise monitoring are listed in Table 6.

Table 6: Action and Limit Levels for Construction Noise

Monitoring Location

Action Level 

Limit Level in dB(A) 

 

Time Period: 07:00-19:00 hours on normal weekdays

NM1A and NM2 

When one or more documented complaints are received

70 dB(A) 1, 2

Note:    1. A correction of +3dB(A) was made to the free field measurement at monitoring station NM1A.
2. No examination has taken place during this reporting period.

Should non-compliance of the environmental quality criteria occur, remedial actions will be 
triggered according to the Event and Action Plan
(refer to Monthly EM&A Report No. 49). 

Data Management and Data QA/QC Control 

All monitoring data will be handled by the ET’s in-house data recording and management system. The monitoring data recorded in the equipment will be downloaded directly from the equipment at the end of each monitoring day.  The downloaded monitoring data will be inputted into a computerized database properly maintained by the ET. 

3.5        Monitoring Schedule

Suspension of impact monitoring for noise was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the last weekly noise monitoring event was conducted on 30 June 2021, while no impact monitoring for noise was conducted during the reporting period.

 

 

 

4        Ecology Monitoring

4.1        General

As required under the Section 8.3.2 of the approved EM&A Manual, the implementation of ecological mitigation measures as detailed in the Section 15 of the EIA report and Appendix C of the approved EM&A Manual shall be routinely audited during the routine environmental audit; and any observations and recommendations shall be reported in periodic EM&A reports.

Among those mitigation measures recommended to avoid or minimize the disturbance to any plants of conservation interest (EM&A reference 8.3.1.1), nested ardeids (EM&A reference 8.3.1.2) and roosted short-nosed fruit bat (EM&A reference 8.3.1.3), the required inspection has already been undertaken in August / September 2014 with the results presented in the submitted respective baseline report.  Therefore, the following sections only address those applicable to this stage of the project, i.e., Section 8.3.2 of the approved EM&A Manual.

4.2        Monitoring Requirement

Monitoring of Plants of Conservation Interest (Platycondon grandiflorus) 

According to Condition 2.6 of Environmental Permit No. EP-487/2014, the Detailed Vegetation Survey Report has located two groups of the protected Platycodon grandiflorus and recommended that the plants should be protected with temporary protective fencing to avoid potential impact from construction activities (such as material storage), and monitor the identified Platycodon grandiflorus on a monthly basis throughout the construction phase to ensure they are not affected by the construction works of the Project. Accordingly, the following monitoring parameters will be undertaken on a monthly basis during the construction period:

    Effective implementation of the protection measures as recommended in the Section 4.1 of the Detailed Vegetation Survey Report 

    Monitoring of the two groups of Platycodon grandiflorus identified during the detailed vegetation survey to ensure they are not affected by the construction works

Monitoring of Nesting Activities of Ardeids in Breeding Season

The project area should be checked monthly in breeding season (April to July) for any potential breeding and nesting activities, and if required, suitably sized buffer area will be recommended to avoid human or machinery disturbance until the nest is abandoned.

Monitoring of Roosting Activities of Ardeids in Peak Wintering Season

The existing ardeid night roost within the project area should be monitored monthly during peak wintering season (November to March) during the construction phase by direct observation from a vantage point (i.e., point count method) in the evening from an hour before sunset to nightfall.

Compensation for Ardeid Roosting Site

An enhancement area proposed as an alternative roosting site for ardeids should be developed during the first phase of the construction.

Compensation of Woodland Habitat

Mitigation measures recommended in the approved Woodland Compensation Plan should be fully and properly implemented, including but not limited to the creation of 0.84 ha woodland compensation on-site and 0.78 ha on-site woodland reinstatement, to mitigate for permanent loss of woodland habitat.

4.3        Inspection Findings

The ecological inspection has been suspended in this reporting period as the construction phase environmental monitoring has been suspended by end of June 2021 in view of the remaining construction activities being merely related to minor defect and cleaning works. There were no ecological impacts from the construction activities, therefore, the monitoring of plants of conservation interest, nesting activities of ardeids in breeding season and roosting activities of ardeids in peak wintering season were no longer applicable.  Tree planting for the Ecological Enhancement Area as the compensation of ardeid roosting site has been completed in July 2021.

Compensation for Ardeid Roosting Site

The site of proposed Ecological Enhancement Area was prepared in the first phase of construction in early 2020. In accordance with the approved Ecological Enhancement Plan, the tree planting within the Ecological Enhancement Area has been implemented and completed in July 2021. Monitoring of the compensation at the Ecological Enhancement Area will be implemented during the operation phase.

Compensation of Woodland Habitat 

To be implemented after construction phase.

 

 

 

5        Landscape & Visual Monitoring

5.1        General

Landscape and visual mitigation measures for the construction phase are listed in the Approved EM&A Manual Table 9.1.

The design, implementation and maintenance of landscape and visual mitigation measures shall be checked bi-weekly to ensure that they are fully realized during the construction phase. The scope of the site audit during construction shall include the following:

    The extent of the agreed works areas should be regularly checked. No construction activities or storage shall be undertaken outside the limit of the works; 

    The progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken; 

    All landscaping works are carried out in accordance with the specifications; and 

    All new plantings are carried out properly and during the right season.

Any potential conflicts between the proposed landscape and visual mitigation measures and any other project works or operational requirements shall be recorded for the Contractor to resolve in an early stage, without compromising the intention of the mitigation measures.

5.2        Inspection Findings

In the Reporting Period, the bi-weekly landscape and visual site inspection has been ceased as the construction phase environmental site audit has been suspended by end of June 2021 in view of completion of construction activities with only minor defect and cleaning works remaining.

In accordance with the approved Visual and Landscape Plan, the landscape planting of the Project was being implemented and has been completed in the reporting month.

 

 

 

6        Site Inspection

6.1        Requirements

According to the approved EM&A Manual, the environmental site inspection shall be formulated by the ET Leader. Weekly environmental site inspections should be carried out to confirm the environmental performance.

6.2        Findings / Deficiencies During the Reporting Period

As construction activities that have the potential to cause significant environmental impacts have already been completed, proposal to suspend environmental site inspection was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, the last weekly environmental site inspection was conducted on 29 June 2021 while no site inspection was undertaken in the Reporting Period.

 

 

 

7        Environmental Complaint, Summons and Prosecution

7.1        Environmental Complaint, Summons and Prosecution

No environmental complaint, summons and prosecution were received in the Reporting Period.  

The statistical summary for environmental complaints is presented in Table 9.

Table 7: Statistics for complaints, notifications of summons and successful prosecutions

Reporting Period 

Cumulative Statistics

 

 

Complaints 

Notifications of summons

Successful prosecutions

This report month

0

0

0

 

 

 

8        Implementation Status of Mitigation Measures

8.1        General Requirements 

The environmental mitigation measures that were recommended in the Implementation Schedule for Environmental Mitigation Measures in the approved EM&A Manual covered the issues of dust, noise, water and waste and are presented in Appendix C.   

The Project shall be implementing the required environmental mitigation measures according to the approved EM&A Manual as subject to the site condition. Good site management was generally implemented by the Contractor carrying out the remaining defect works in this Reporting Month.

8.2        Tentative Construction Activities in the Coming Month

There would not be any construction activities to be undertaken for the Project in the coming month, as all the construction activities and minor defect works were completed within this reporting month.

8.3        Key Issues for the Coming Month

All construction activities have already been completed. There are no future key issues concerned.

 

 

 

9        Conclusion

Construction activities that have the potential to cause significant environmental impacts have already been completed, while the remaining site activities were merely related to minor defect and cleaning works which were also completed in the reporting month. For the EM&A programme, the proposal for suspension of the construction phase environmental monitoring by end of June 2021 was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. Therefore, no weekly environmental site audits or impact monitoring for noise were carried out during the reporting period. With the completion of landscape planting and other greening works in the reporting month, the EM&A programme of construction phase has been completed in August 2021.